milestone->common = $lang->projectCommon . '里程碑報告'; $lang->milestone->index = '報告首頁'; $lang->milestone->title = '里程碑報告'; $lang->milestone->name = '里程碑名稱'; $lang->milestone->stage = '里程碑階段'; $lang->milestone->save = '保存'; $lang->milestone->indexAction = '里程碑報告'; $lang->milestone->startedWeeks = '開始周數'; $lang->milestone->finishedWeeks = '結束周數'; $lang->milestone->offset = '里程碑工期偏差'; $lang->milestone->processCommon = $lang->projectCommon . '當前進展狀況'; $lang->milestone->process = $lang->projectCommon . '進度'; $lang->milestone->executionCost = $lang->projectCommon . '成本'; $lang->milestone->toNow = '到目前為止'; $lang->milestone->targetRange = '目標控制範圍'; $lang->milestone->ge = '大於等於'; $lang->milestone->le = '小於等於'; $lang->milestone->analysis = '分析結果'; $lang->milestone->PV = '計劃完成的工作(PV)'; $lang->milestone->EV = '實際完成的工作(EV)'; $lang->milestone->AC = '實際花費的成本(AC)'; $lang->milestone->SPI = $lang->projectCommon . '進度績效(SPI)'; $lang->milestone->CPI = $lang->projectCommon . '成本績效(CPI)'; $lang->milestone->SV = '進度偏差率(SV%)'; $lang->milestone->CV = '成本偏差率(CV%)'; $lang->milestone->workHours = '工作量(人時)'; $lang->milestone->allStage = '工程階段'; $lang->milestone->devHours = '研發工作量'; $lang->milestone->toHours = '返工工作量'; $lang->milestone->reviewHours = '評審工作量'; $lang->milestone->qaHours = '測試工作量'; $lang->milestone->rowSummary = '工作量小計'; $lang->milestone->rowPercent = '分佈百分比(%)'; $lang->milestone->colPercent = '占工作量百分比(%)'; $lang->milestone->colSummary = '總和'; $lang->milestone->qatoDev = '測試研發比'; $lang->milestone->executionRisk = '5.' . $lang->projectCommon . '風險(優先最高的前五項風險)'; $lang->milestone->riskCountermove = '風險對策'; $lang->milestone->riskDescriptio = '風險描述'; $lang->milestone->riskPossibility = '可能性'; $lang->milestone->riskSeriousness = '嚴重性'; $lang->milestone->riskFactor = '風險係數'; $lang->milestone->riskMeasures = '風險對策'; $lang->milestone->riskAccumulate = '累積的高風險'; $lang->milestone->otherIssue = '其它問題'; $lang->milestone->issueSolutions = '問題及解決建議'; $lang->milestone->issueDescription = '問題描述'; $lang->milestone->issuePropose = '解決建議'; $lang->milestone->demandStatus = '4.用戶需求狀況分析'; $lang->milestone->storyUnit = '單位:Item'; $lang->milestone->engineeringStage = '工程階段'; $lang->milestone->rateChange = '需求變化率'; $lang->milestone->originalStory = '原始需求數量'; $lang->milestone->modifyNumber = '變更後需求總數'; $lang->milestone->changeStory = '變更的需求數'; $lang->milestone->paogressForecast = $lang->projectCommon . '進展預測'; $lang->milestone->duration = '工期(天)'; $lang->milestone->cost = '成本(人時)'; $lang->milestone->forecastResults = '預測結果分析'; $lang->milestone->plannedValue = '計劃值'; $lang->milestone->predictedValue = '預測值'; $lang->milestone->predictedValueDesc = '計算公式:如果' . $lang->projectCommon . '進度績效(SPI)=0,那麼預測值=0,否則,預測值=計劃值 除以 ' . $lang->projectCommon . '進度績效(SPI)'; $lang->milestone->periodDeviation = '工期偏差'; $lang->milestone->costDeviation = '成本偏差'; $lang->milestone->nextStage = '下一里程碑階段'; $lang->milestone->overallProject = $lang->projectCommon . '總體'; $lang->milestone->corrective = '糾偏措施'; $lang->milestone->timeOverrun = '總工期將超出:%s天。'; $lang->milestone->costOverrun = '總成本將超出:%s個單位。'; $lang->milestone->saveOtherProblem = '保存其他問題'; $lang->milestone->chart = new stdclass(); $lang->milestone->chart->title = '到目前為止' . $lang->projectCommon . '進展趨勢圖'; $lang->milestone->chart->time = '第'; $lang->milestone->chart->week = '周'; $lang->milestone->chart->month = '月'; $lang->milestone->chart->workhour = '研發工作量分析圖'; $lang->milestone->otherproblem = '6.其它問題'; $lang->milestone->problemandsuggest = '問題及解決建議'; $lang->milestone->suggest = '解決建議'; $lang->milestone->needhelp = '是否需要高層支持?'; $lang->milestone->prodescr = '問題描述'; $lang->milestone->reviewHoursTip = '評審工作量 = 評審時長 * 評審人數'; $lang->milestone->toHoursTip = '返工工作量統計的是研發任務被激活之後,重新消耗的工時'; $lang->milestone->quality = new stdclass(); $lang->milestone->quality->total = '合計'; $lang->milestone->quality->identify = '缺陷識別階段'; $lang->milestone->quality->injection = '缺陷注入階段'; $lang->milestone->quality->scale = '規模'; $lang->milestone->quality->identifyRate = '缺陷識別率'; $lang->milestone->quality->injectionRate = '缺陷注入率'; $lang->milestone->options = '操作'; $lang->milestone->milestoneHelpNotice = <<PV 計劃完成的工作 計算方式:
1)任務所屬階段是當前里程碑,累加預計工時
2)當前里程碑階段之前的所有階段下的任務,累加預計工時

統計範圍:

1)為避免重複計算,只包含子任務,不包括父任務
2)不包括已刪除的任務
3)不包括已取消的任務
4)不包括已刪除執行中的任務

EV實際完成的工作

計算方式:
1)任務所屬階段是當前里程碑:
        任務狀態為已完成,累加預計工時
        任務狀態為已關閉且關閉原因為已完成,累加預計工時
        任務狀態為進行中、已暫停,累加 預計工時×完成進度
2)當前里程碑階段之前的所有階段下的任務:
        任務狀態為已完成,累加預計工時
        任務狀態為已關閉且關閉原因為已完成,累加預計工時
        任務狀態為進行中、已暫停,累加 預計工時×完成進度

統計範圍:

1)為避免重複計算,只包含子任務,不包括父任務
2)不包括已刪除的任務
3)不包括已取消的任務
4)不包括已刪除執行中的任務
5)消耗工時不為0的任務
6)完成進度=已消耗工時÷(已消耗工時+剩餘工時)

AC 實際花費(消耗)的成本

計算方式:
1)當前里程碑中所有消耗的工時
2)當前里程碑階段之前的所有階段下消耗的工時

統計範圍:

1)消耗的工時包括任務、需求、Bug、用例、版本、測試單、問題、風險、文檔、評審的耗時
2)為避免重複計算,只包含子任務,不包括父任務
3)包括已刪除的任務、需求、Bug、用例、版本、測試單、問題、風險、文檔、評審的耗時
4)包括已刪除執行中任務、需求、Bug、用例、版本、測試單、文檔的耗時
5)包括取消的任務、問題、風險的耗時

SV(%)進度偏差率

計算方式:SV(%) = -1 * (1 - (EV / PV))%

CV(%) 成本偏差率

計算方式:CV(%) = -1 * (1 - (EV / AC))%

SPI 進度性能指標

計算方式:SPI = EV / PV

CPI成本性能指標

計算方式:CPI = EV / AC EOD; $lang->milestone->soFarHelpNotice = <<PV計劃完成的工作 計算方式:
1)任務預計截止日期在今天結束時間之前,累加預計工時
2)任務預計開始日期小於今天結束時間,截止日期大於今天結束時間,累加(任務的預計工時 ÷ 任務工期天數)× 任務預計開始到本週結束日期的天數

統計範圍:

1)為避免重複計算,只包含子任務,不包括父任務
2)不包括刪除的任務
3)不包括取消的任務
4)不包括已刪除執行中的任務
5)今天結束時間是今天的23:59:59
6)任務未填寫預計開始日期,預計開始日期預設取任務所屬階段的計劃開始日期
7)任務未填寫預計截止日期,預計截止日期預設取任務所屬階段的計劃完成日期
8)計算公式只計算工作日

EV實際完成的工作

計算方式:
1)任務狀態為已完成,累加預計工時
2)任務狀態為已關閉且關閉原因為已完成,累加預計工時
3)任務狀態為進行中、已暫停,累加 預計工時×完成進度

統計範圍:

1)今天結束時間之前,今天結束時間是今天的23:59:59
2)為避免重複計算,只包含子任務,不包括父任務
3)不包括已刪除的任務
4)不包括已取消的任務
5)不包括已刪除執行中的任務
6)消耗工時不為0的任務
7)完成進度=已消耗工時÷(已消耗工時+剩餘工時)

AC 實際花費(消耗)的成本

計算方式:
1)累加今天結束時間之前所有消耗的工時

統計範圍:

1)消耗的工時包括任務、需求、Bug、用例、版本、測試單、問題、風險、文檔、評審的耗時
2)為避免重複計算,只包含子任務,不包括父任務
3)包括已刪除的任務、需求、Bug、用例、版本、測試單、問題、風險、文檔、評審的耗時
4)包括已刪除執行中任務、需求、Bug、用例、版本、測試單、文檔的耗時
5)包括取消的任務、問題、風險的耗時
6)今天結束時間是今天的23:59:59

SV(%)進度偏差率

計算方式:SV(%) = -1 * (1 - (EV / PV))%

CV(%) 成本偏差率

計算方式:CV(%) = -1 * (1 - (EV / AC))%

SPI 進度性能指標

計算方式:SPI = EV / PV

CPI成本性能指標

計算方式:CPI = EV / AC EOD;