2023-05-16 10:50:42 +08:00

199 lines
10 KiB
PHP
Raw Permalink Blame History

This file contains ambiguous Unicode characters

This file contains Unicode characters that might be confused with other characters. If you think that this is intentional, you can safely ignore this warning. Use the Escape button to reveal them.

<?php
$lang->milestone->common = $lang->projectCommon . '里程碑报告';
$lang->milestone->index = '报告首页';
$lang->milestone->title = '里程碑报告';
$lang->milestone->name = '里程碑名称';
$lang->milestone->stage = '里程碑阶段';
$lang->milestone->save = '保存';
$lang->milestone->indexAction = '里程碑报告';
$lang->milestone->startedWeeks = '开始周数';
$lang->milestone->finishedWeeks = '结束周数';
$lang->milestone->offset = '里程碑工期偏差';
$lang->milestone->processCommon = $lang->projectCommon . '当前进展状况';
$lang->milestone->process = $lang->projectCommon . '进度';
$lang->milestone->executionCost = $lang->projectCommon . '成本';
$lang->milestone->toNow = '到目前为止';
$lang->milestone->targetRange = '目标控制范围';
$lang->milestone->ge = '大于等于';
$lang->milestone->le = '小于等于';
$lang->milestone->analysis = '分析结果';
$lang->milestone->PV = '计划完成的工作(PV)';
$lang->milestone->EV = '实际完成的工作(EV)';
$lang->milestone->AC = '实际花费的成本(AC)';
$lang->milestone->SPI = $lang->projectCommon . '进度绩效(SPI)';
$lang->milestone->CPI = $lang->projectCommon . '成本绩效(CPI)';
$lang->milestone->SV = '进度偏差率(SV%)';
$lang->milestone->CV = '成本偏差率(CV%)';
$lang->milestone->workHours = '工作量(人时)';
$lang->milestone->allStage = '工程阶段';
$lang->milestone->devHours = '研发工作量';
$lang->milestone->toHours = '返工工作量';
$lang->milestone->reviewHours = '评审工作量';
$lang->milestone->qaHours = '测试工作量';
$lang->milestone->rowSummary = '工作量小计';
$lang->milestone->rowPercent = '分布百分比(%)';
$lang->milestone->colPercent = '占工作量百分比(%)';
$lang->milestone->colSummary = '总和';
$lang->milestone->qatoDev = '测试研发比';
$lang->milestone->executionRisk = '5.' . $lang->projectCommon . '风险(优先最高的前五项风险)';
$lang->milestone->riskCountermove = '风险对策';
$lang->milestone->riskDescriptio = '风险描述';
$lang->milestone->riskPossibility = '可能性';
$lang->milestone->riskSeriousness = '严重性';
$lang->milestone->riskFactor = '风险系数';
$lang->milestone->riskMeasures = '风险对策';
$lang->milestone->riskAccumulate = '累积的高风险';
$lang->milestone->otherIssue = '其它问题';
$lang->milestone->issueSolutions = '问题及解决建议';
$lang->milestone->issueDescription = '问题描述';
$lang->milestone->issuePropose = '解决建议';
$lang->milestone->demandStatus = '4.用户需求状况分析';
$lang->milestone->storyUnit = '单位:Item';
$lang->milestone->engineeringStage = '工程阶段';
$lang->milestone->rateChange = '需求变化率';
$lang->milestone->originalStory = '原始需求数量';
$lang->milestone->modifyNumber = '变更后需求总数';
$lang->milestone->changeStory = '变更的需求数';
$lang->milestone->paogressForecast = $lang->projectCommon . '进展预测';
$lang->milestone->duration = '工期(天)';
$lang->milestone->cost = '成本(人时)';
$lang->milestone->forecastResults = '预测结果分析';
$lang->milestone->plannedValue = '计划值';
$lang->milestone->predictedValue = '预测值';
$lang->milestone->predictedValueDesc = '计算公式:如果' . $lang->projectCommon . '进度绩效(SPI)=0那么预测值=0否则预测值=计划值 除以 ' . $lang->projectCommon . '进度绩效(SPI)';
$lang->milestone->periodDeviation = '工期偏差';
$lang->milestone->costDeviation = '成本偏差';
$lang->milestone->nextStage = '下一里程碑阶段';
$lang->milestone->overallProject = $lang->projectCommon . '总体';
$lang->milestone->corrective = '纠偏措施';
$lang->milestone->timeOverrun = '总工期将超出:%s天。';
$lang->milestone->costOverrun = '总成本将超出:%s个单位。';
$lang->milestone->saveOtherProblem = '保存其他问题';
$lang->milestone->chart = new stdclass();
$lang->milestone->chart->title = '到目前为止' . $lang->projectCommon . '进展趋势图';
$lang->milestone->chart->time = '第';
$lang->milestone->chart->week = '周';
$lang->milestone->chart->month = '月';
$lang->milestone->chart->workhour = '研发工作量分析图';
$lang->milestone->otherproblem = '6.其它问题';
$lang->milestone->problemandsuggest = '问题及解决建议';
$lang->milestone->suggest = '解决建议';
$lang->milestone->needhelp = '是否需要高层支持?';
$lang->milestone->prodescr = '问题描述';
$lang->milestone->reviewHoursTip = '评审工作量 = 评审时长 * 评审人数';
$lang->milestone->toHoursTip = '返工工作量统计的是研发任务被激活之后,重新消耗的工时';
$lang->milestone->quality = new stdclass();
$lang->milestone->quality->total = '合计';
$lang->milestone->quality->identify = '缺陷识别阶段';
$lang->milestone->quality->injection = '缺陷注入阶段';
$lang->milestone->quality->scale = '规模';
$lang->milestone->quality->identifyRate = '缺陷识别率';
$lang->milestone->quality->injectionRate = '缺陷注入率';
$lang->milestone->options = '操作';
$lang->milestone->milestoneHelpNotice = <<<EOD
<h2>PV 计划完成的工作</h2>
计算方式:
<br />1任务所属阶段是当前里程碑累加预计工时
<br />2当前里程碑阶段之前的所有阶段下的任务累加预计工时
<p>统计范围:</p>
1为避免重复计算只包含子任务不包括父任务
<br />2不包括已删除的任务
<br />3不包括已取消的任务
<br />4不包括已删除执行中的任务
<h2>EV实际完成的工作</h2>
计算方式:
<br />1任务所属阶段是当前里程碑
<br />&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;任务状态为已完成,累加预计工时
<br />&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;任务状态为已关闭且关闭原因为已完成,累加预计工时
<br />&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;任务状态为进行中、已暂停,累加 预计工时×完成进度
<br />2当前里程碑阶段之前的所有阶段下的任务
<br />&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;任务状态为已完成,累加预计工时
<br />&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;任务状态为已关闭且关闭原因为已完成,累加预计工时
<br />&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;任务状态为进行中、已暂停,累加 预计工时×完成进度
<p>统计范围:</p>
1为避免重复计算只包含子任务不包括父任务
<br />2不包括已删除的任务
<br />3不包括已取消的任务
<br />4不包括已删除执行中的任务
<br />5消耗工时不为0的任务
<br />6完成进度=已消耗工时÷(已消耗工时+剩余工时)
<h2>AC 实际花费(消耗)的成本</h2>
计算方式:
<br />1当前里程碑中所有消耗的工时
<br />2当前里程碑阶段之前的所有阶段下消耗的工时
<p>统计范围:</p>
1消耗的工时包括任务、需求、Bug、用例、版本、测试单、问题、风险、文档、评审的耗时
<br />2为避免重复计算只包含子任务不包括父任务
<br />3包括已删除的任务、需求、Bug、用例、版本、测试单、问题、风险、文档、评审的耗时
<br />4包括已删除执行中任务、需求、Bug、用例、版本、测试单、文档的耗时
<br />5包括取消的任务、问题、风险的耗时
<h2>SV(%)进度偏差率</h2>
计算方式SV(%) = -1 * (1 - (EV / PV))%
<h2>CV(%) 成本偏差率</h2>
计算方式CV(%) = -1 * (1 - (EV / AC))%
<h2>SPI 进度性能指标</h2>
计算方式SPI = EV / PV
<h2>CPI成本性能指标</h2>
计算方式CPI = EV / AC
EOD;
$lang->milestone->soFarHelpNotice = <<<EOD
<h2>PV计划完成的工作</h2>
计算方式:
<br />1任务预计截止日期在今天结束时间之前累加预计工时
<br />2任务预计开始日期小于今天结束时间截止日期大于今天结束时间累加任务的预计工时 ÷ 任务工期天数)× 任务预计开始到本周结束日期的天数
<p>统计范围:</p>
1为避免重复计算只包含子任务不包括父任务
<br />2不包括删除的任务
<br />3不包括取消的任务
<br />4不包括已删除执行中的任务
<br />5今天结束时间是今天的23:59:59
<br />6任务未填写预计开始日期预计开始日期默认取任务所属阶段的计划开始日期
<br />7任务未填写预计截止日期预计截止日期默认取任务所属阶段的计划完成日期
<br />8计算公式只计算工作日
<h2>EV实际完成的工作</h2>
计算方式:
<br />1任务状态为已完成累加预计工时
<br />2任务状态为已关闭且关闭原因为已完成累加预计工时
<br />3任务状态为进行中、已暂停累加 预计工时×完成进度
<p>统计范围:</p>
1今天结束时间之前今天结束时间是今天的23:59:59
<br />2为避免重复计算只包含子任务不包括父任务
<br />3不包括已删除的任务
<br />4不包括已取消的任务
<br />5不包括已删除执行中的任务
<br />6消耗工时不为0的任务
<br />7完成进度=已消耗工时÷(已消耗工时+剩余工时)
<h2>AC 实际花费(消耗)的成本</h2>
计算方式:
<br />1累加今天结束时间之前所有消耗的工时
<p>统计范围:</p>
1消耗的工时包括任务、需求、Bug、用例、版本、测试单、问题、风险、文档、评审的耗时
<br />2为避免重复计算只包含子任务不包括父任务
<br />3包括已删除的任务、需求、Bug、用例、版本、测试单、问题、风险、文档、评审的耗时
<br />4包括已删除执行中任务、需求、Bug、用例、版本、测试单、文档的耗时
<br />5包括取消的任务、问题、风险的耗时
<br />6今天结束时间是今天的23:59:59
<h2>SV(%)进度偏差率</h2>
计算方式SV(%) = -1 * (1 - (EV / PV))%
<h2>CV(%) 成本偏差率</h2>
计算方式CV(%) = -1 * (1 - (EV / AC))%
<h2>SPI 进度性能指标</h2>
计算方式SPI = EV / PV
<h2>CPI成本性能指标</h2>
计算方式CPI = EV / AC