199 lines
10 KiB
PHP
199 lines
10 KiB
PHP
<?php
|
||
$lang->milestone->common = $lang->projectCommon . '里程碑报告';
|
||
$lang->milestone->index = '报告首页';
|
||
$lang->milestone->title = '里程碑报告';
|
||
$lang->milestone->name = '里程碑名称';
|
||
$lang->milestone->stage = '里程碑阶段';
|
||
$lang->milestone->save = '保存';
|
||
|
||
$lang->milestone->indexAction = '里程碑报告';
|
||
|
||
$lang->milestone->startedWeeks = '开始周数';
|
||
$lang->milestone->finishedWeeks = '结束周数';
|
||
$lang->milestone->offset = '里程碑工期偏差';
|
||
|
||
$lang->milestone->processCommon = $lang->projectCommon . '当前进展状况';
|
||
$lang->milestone->process = $lang->projectCommon . '进度';
|
||
$lang->milestone->executionCost = $lang->projectCommon . '成本';
|
||
$lang->milestone->toNow = '到目前为止';
|
||
$lang->milestone->targetRange = '目标控制范围';
|
||
$lang->milestone->ge = '大于等于';
|
||
$lang->milestone->le = '小于等于';
|
||
$lang->milestone->analysis = '分析结果';
|
||
$lang->milestone->PV = '计划完成的工作(PV)';
|
||
$lang->milestone->EV = '实际完成的工作(EV)';
|
||
$lang->milestone->AC = '实际花费的成本(AC)';
|
||
$lang->milestone->SPI = $lang->projectCommon . '进度绩效(SPI)';
|
||
$lang->milestone->CPI = $lang->projectCommon . '成本绩效(CPI)';
|
||
$lang->milestone->SV = '进度偏差率(SV%)';
|
||
$lang->milestone->CV = '成本偏差率(CV%)';
|
||
|
||
$lang->milestone->workHours = '工作量(人时)';
|
||
$lang->milestone->allStage = '工程阶段';
|
||
$lang->milestone->devHours = '研发工作量';
|
||
$lang->milestone->toHours = '返工工作量';
|
||
$lang->milestone->reviewHours = '评审工作量';
|
||
$lang->milestone->qaHours = '测试工作量';
|
||
$lang->milestone->rowSummary = '工作量小计';
|
||
$lang->milestone->rowPercent = '分布百分比(%)';
|
||
$lang->milestone->colPercent = '占工作量百分比(%)';
|
||
$lang->milestone->colSummary = '总和';
|
||
$lang->milestone->qatoDev = '测试研发比';
|
||
|
||
$lang->milestone->executionRisk = '5.' . $lang->projectCommon . '风险(优先最高的前五项风险)';
|
||
$lang->milestone->riskCountermove = '风险对策';
|
||
$lang->milestone->riskDescriptio = '风险描述';
|
||
$lang->milestone->riskPossibility = '可能性';
|
||
$lang->milestone->riskSeriousness = '严重性';
|
||
$lang->milestone->riskFactor = '风险系数';
|
||
$lang->milestone->riskMeasures = '风险对策';
|
||
$lang->milestone->riskAccumulate = '累积的高风险';
|
||
|
||
$lang->milestone->otherIssue = '其它问题';
|
||
$lang->milestone->issueSolutions = '问题及解决建议';
|
||
$lang->milestone->issueDescription = '问题描述';
|
||
$lang->milestone->issuePropose = '解决建议';
|
||
|
||
$lang->milestone->demandStatus = '4.用户需求状况分析';
|
||
$lang->milestone->storyUnit = '单位:Item';
|
||
$lang->milestone->engineeringStage = '工程阶段';
|
||
$lang->milestone->rateChange = '需求变化率';
|
||
$lang->milestone->originalStory = '原始需求数量';
|
||
$lang->milestone->modifyNumber = '变更后需求总数';
|
||
$lang->milestone->changeStory = '变更的需求数';
|
||
|
||
$lang->milestone->paogressForecast = $lang->projectCommon . '进展预测';
|
||
$lang->milestone->duration = '工期(天)';
|
||
$lang->milestone->cost = '成本(人时)';
|
||
$lang->milestone->forecastResults = '预测结果分析';
|
||
$lang->milestone->plannedValue = '计划值';
|
||
$lang->milestone->predictedValue = '预测值';
|
||
$lang->milestone->predictedValueDesc = '计算公式:如果' . $lang->projectCommon . '进度绩效(SPI)=0,那么预测值=0,否则,预测值=计划值 除以 ' . $lang->projectCommon . '进度绩效(SPI)';
|
||
$lang->milestone->periodDeviation = '工期偏差';
|
||
$lang->milestone->costDeviation = '成本偏差';
|
||
$lang->milestone->nextStage = '下一里程碑阶段';
|
||
$lang->milestone->overallProject = $lang->projectCommon . '总体';
|
||
$lang->milestone->corrective = '纠偏措施';
|
||
$lang->milestone->timeOverrun = '总工期将超出:%s天。';
|
||
$lang->milestone->costOverrun = '总成本将超出:%s个单位。';
|
||
$lang->milestone->saveOtherProblem = '保存其他问题';
|
||
|
||
$lang->milestone->chart = new stdclass();
|
||
$lang->milestone->chart->title = '到目前为止' . $lang->projectCommon . '进展趋势图';
|
||
$lang->milestone->chart->time = '第';
|
||
$lang->milestone->chart->week = '周';
|
||
$lang->milestone->chart->month = '月';
|
||
$lang->milestone->chart->workhour = '研发工作量分析图';
|
||
|
||
$lang->milestone->otherproblem = '6.其它问题';
|
||
$lang->milestone->problemandsuggest = '问题及解决建议';
|
||
$lang->milestone->suggest = '解决建议';
|
||
$lang->milestone->needhelp = '是否需要高层支持?';
|
||
$lang->milestone->prodescr = '问题描述';
|
||
|
||
$lang->milestone->reviewHoursTip = '评审工作量 = 评审时长 * 评审人数';
|
||
$lang->milestone->toHoursTip = '返工工作量统计的是研发任务被激活之后,重新消耗的工时';
|
||
|
||
$lang->milestone->quality = new stdclass();
|
||
$lang->milestone->quality->total = '合计';
|
||
$lang->milestone->quality->identify = '缺陷识别阶段';
|
||
$lang->milestone->quality->injection = '缺陷注入阶段';
|
||
$lang->milestone->quality->scale = '规模';
|
||
$lang->milestone->quality->identifyRate = '缺陷识别率';
|
||
$lang->milestone->quality->injectionRate = '缺陷注入率';
|
||
|
||
$lang->milestone->options = '操作';
|
||
|
||
$lang->milestone->milestoneHelpNotice = <<<EOD
|
||
<h2>PV 计划完成的工作</h2>
|
||
计算方式:
|
||
<br />1)任务所属阶段是当前里程碑,累加预计工时
|
||
<br />2)当前里程碑阶段之前的所有阶段下的任务,累加预计工时
|
||
<p>统计范围:</p>
|
||
1)为避免重复计算,只包含子任务,不包括父任务
|
||
<br />2)不包括已删除的任务
|
||
<br />3)不包括已取消的任务
|
||
<br />4)不包括已删除执行中的任务
|
||
<h2>EV实际完成的工作</h2>
|
||
计算方式:
|
||
<br />1)任务所属阶段是当前里程碑:
|
||
<br /> 任务状态为已完成,累加预计工时
|
||
<br /> 任务状态为已关闭且关闭原因为已完成,累加预计工时
|
||
<br /> 任务状态为进行中、已暂停,累加 预计工时×完成进度
|
||
<br />2)当前里程碑阶段之前的所有阶段下的任务:
|
||
<br /> 任务状态为已完成,累加预计工时
|
||
<br /> 任务状态为已关闭且关闭原因为已完成,累加预计工时
|
||
<br /> 任务状态为进行中、已暂停,累加 预计工时×完成进度
|
||
<p>统计范围:</p>
|
||
1)为避免重复计算,只包含子任务,不包括父任务
|
||
<br />2)不包括已删除的任务
|
||
<br />3)不包括已取消的任务
|
||
<br />4)不包括已删除执行中的任务
|
||
<br />5)消耗工时不为0的任务
|
||
<br />6)完成进度=已消耗工时÷(已消耗工时+剩余工时)
|
||
<h2>AC 实际花费(消耗)的成本</h2>
|
||
计算方式:
|
||
<br />1)当前里程碑中所有消耗的工时
|
||
<br />2)当前里程碑阶段之前的所有阶段下消耗的工时
|
||
<p>统计范围:</p>
|
||
1)消耗的工时包括任务、需求、Bug、用例、版本、测试单、问题、风险、文档、评审的耗时
|
||
<br />2)为避免重复计算,只包含子任务,不包括父任务
|
||
<br />3)包括已删除的任务、需求、Bug、用例、版本、测试单、问题、风险、文档、评审的耗时
|
||
<br />4)包括已删除执行中任务、需求、Bug、用例、版本、测试单、文档的耗时
|
||
<br />5)包括取消的任务、问题、风险的耗时
|
||
<h2>SV(%)进度偏差率</h2>
|
||
计算方式:SV(%) = -1 * (1 - (EV / PV))%
|
||
<h2>CV(%) 成本偏差率</h2>
|
||
计算方式:CV(%) = -1 * (1 - (EV / AC))%
|
||
<h2>SPI 进度性能指标</h2>
|
||
计算方式:SPI = EV / PV
|
||
<h2>CPI成本性能指标</h2>
|
||
计算方式:CPI = EV / AC
|
||
EOD;
|
||
$lang->milestone->soFarHelpNotice = <<<EOD
|
||
<h2>PV计划完成的工作</h2>
|
||
计算方式:
|
||
<br />1)任务预计截止日期在今天结束时间之前,累加预计工时
|
||
<br />2)任务预计开始日期小于今天结束时间,截止日期大于今天结束时间,累加(任务的预计工时 ÷ 任务工期天数)× 任务预计开始到本周结束日期的天数
|
||
<p>统计范围:</p>
|
||
1)为避免重复计算,只包含子任务,不包括父任务
|
||
<br />2)不包括删除的任务
|
||
<br />3)不包括取消的任务
|
||
<br />4)不包括已删除执行中的任务
|
||
<br />5)今天结束时间是今天的23:59:59
|
||
<br />6)任务未填写预计开始日期,预计开始日期默认取任务所属阶段的计划开始日期
|
||
<br />7)任务未填写预计截止日期,预计截止日期默认取任务所属阶段的计划完成日期
|
||
<br />8)计算公式只计算工作日
|
||
<h2>EV实际完成的工作</h2>
|
||
计算方式:
|
||
<br />1)任务状态为已完成,累加预计工时
|
||
<br />2)任务状态为已关闭且关闭原因为已完成,累加预计工时
|
||
<br />3)任务状态为进行中、已暂停,累加 预计工时×完成进度
|
||
<p>统计范围:</p>
|
||
1)今天结束时间之前,今天结束时间是今天的23:59:59
|
||
<br />2)为避免重复计算,只包含子任务,不包括父任务
|
||
<br />3)不包括已删除的任务
|
||
<br />4)不包括已取消的任务
|
||
<br />5)不包括已删除执行中的任务
|
||
<br />6)消耗工时不为0的任务
|
||
<br />7)完成进度=已消耗工时÷(已消耗工时+剩余工时)
|
||
<h2>AC 实际花费(消耗)的成本</h2>
|
||
计算方式:
|
||
<br />1)累加今天结束时间之前所有消耗的工时
|
||
<p>统计范围:</p>
|
||
1)消耗的工时包括任务、需求、Bug、用例、版本、测试单、问题、风险、文档、评审的耗时
|
||
<br />2)为避免重复计算,只包含子任务,不包括父任务
|
||
<br />3)包括已删除的任务、需求、Bug、用例、版本、测试单、问题、风险、文档、评审的耗时
|
||
<br />4)包括已删除执行中任务、需求、Bug、用例、版本、测试单、文档的耗时
|
||
<br />5)包括取消的任务、问题、风险的耗时
|
||
<br />6)今天结束时间是今天的23:59:59
|
||
<h2>SV(%)进度偏差率</h2>
|
||
计算方式:SV(%) = -1 * (1 - (EV / PV))%
|
||
<h2>CV(%) 成本偏差率</h2>
|
||
计算方式:CV(%) = -1 * (1 - (EV / AC))%
|
||
<h2>SPI 进度性能指标</h2>
|
||
计算方式:SPI = EV / PV
|
||
<h2>CPI成本性能指标</h2>
|
||
计算方式:CPI = EV / AC
|
||
EOD;
|