2023-05-16 10:50:42 +08:00

199 lines
10 KiB
PHP
Raw Permalink Blame History

This file contains ambiguous Unicode characters

This file contains Unicode characters that might be confused with other characters. If you think that this is intentional, you can safely ignore this warning. Use the Escape button to reveal them.

<?php
$lang->milestone->common = $lang->projectCommon . '里程碑報告';
$lang->milestone->index = '報告首頁';
$lang->milestone->title = '里程碑報告';
$lang->milestone->name = '里程碑名稱';
$lang->milestone->stage = '里程碑階段';
$lang->milestone->save = '保存';
$lang->milestone->indexAction = '里程碑報告';
$lang->milestone->startedWeeks = '開始周數';
$lang->milestone->finishedWeeks = '結束周數';
$lang->milestone->offset = '里程碑工期偏差';
$lang->milestone->processCommon = $lang->projectCommon . '當前進展狀況';
$lang->milestone->process = $lang->projectCommon . '進度';
$lang->milestone->executionCost = $lang->projectCommon . '成本';
$lang->milestone->toNow = '到目前為止';
$lang->milestone->targetRange = '目標控制範圍';
$lang->milestone->ge = '大於等於';
$lang->milestone->le = '小於等於';
$lang->milestone->analysis = '分析結果';
$lang->milestone->PV = '計劃完成的工作(PV)';
$lang->milestone->EV = '實際完成的工作(EV)';
$lang->milestone->AC = '實際花費的成本(AC)';
$lang->milestone->SPI = $lang->projectCommon . '進度績效(SPI)';
$lang->milestone->CPI = $lang->projectCommon . '成本績效(CPI)';
$lang->milestone->SV = '進度偏差率(SV%)';
$lang->milestone->CV = '成本偏差率(CV%)';
$lang->milestone->workHours = '工作量(人時)';
$lang->milestone->allStage = '工程階段';
$lang->milestone->devHours = '研發工作量';
$lang->milestone->toHours = '返工工作量';
$lang->milestone->reviewHours = '評審工作量';
$lang->milestone->qaHours = '測試工作量';
$lang->milestone->rowSummary = '工作量小計';
$lang->milestone->rowPercent = '分佈百分比(%)';
$lang->milestone->colPercent = '占工作量百分比(%)';
$lang->milestone->colSummary = '總和';
$lang->milestone->qatoDev = '測試研發比';
$lang->milestone->executionRisk = '5.' . $lang->projectCommon . '風險(優先最高的前五項風險)';
$lang->milestone->riskCountermove = '風險對策';
$lang->milestone->riskDescriptio = '風險描述';
$lang->milestone->riskPossibility = '可能性';
$lang->milestone->riskSeriousness = '嚴重性';
$lang->milestone->riskFactor = '風險係數';
$lang->milestone->riskMeasures = '風險對策';
$lang->milestone->riskAccumulate = '累積的高風險';
$lang->milestone->otherIssue = '其它問題';
$lang->milestone->issueSolutions = '問題及解決建議';
$lang->milestone->issueDescription = '問題描述';
$lang->milestone->issuePropose = '解決建議';
$lang->milestone->demandStatus = '4.用戶需求狀況分析';
$lang->milestone->storyUnit = '單位:Item';
$lang->milestone->engineeringStage = '工程階段';
$lang->milestone->rateChange = '需求變化率';
$lang->milestone->originalStory = '原始需求數量';
$lang->milestone->modifyNumber = '變更後需求總數';
$lang->milestone->changeStory = '變更的需求數';
$lang->milestone->paogressForecast = $lang->projectCommon . '進展預測';
$lang->milestone->duration = '工期(天)';
$lang->milestone->cost = '成本(人時)';
$lang->milestone->forecastResults = '預測結果分析';
$lang->milestone->plannedValue = '計劃值';
$lang->milestone->predictedValue = '預測值';
$lang->milestone->predictedValueDesc = '計算公式:如果' . $lang->projectCommon . '進度績效(SPI)=0那麼預測值=0否則預測值=計劃值 除以 ' . $lang->projectCommon . '進度績效(SPI)';
$lang->milestone->periodDeviation = '工期偏差';
$lang->milestone->costDeviation = '成本偏差';
$lang->milestone->nextStage = '下一里程碑階段';
$lang->milestone->overallProject = $lang->projectCommon . '總體';
$lang->milestone->corrective = '糾偏措施';
$lang->milestone->timeOverrun = '總工期將超出:%s天。';
$lang->milestone->costOverrun = '總成本將超出:%s個單位。';
$lang->milestone->saveOtherProblem = '保存其他問題';
$lang->milestone->chart = new stdclass();
$lang->milestone->chart->title = '到目前為止' . $lang->projectCommon . '進展趨勢圖';
$lang->milestone->chart->time = '第';
$lang->milestone->chart->week = '周';
$lang->milestone->chart->month = '月';
$lang->milestone->chart->workhour = '研發工作量分析圖';
$lang->milestone->otherproblem = '6.其它問題';
$lang->milestone->problemandsuggest = '問題及解決建議';
$lang->milestone->suggest = '解決建議';
$lang->milestone->needhelp = '是否需要高層支持?';
$lang->milestone->prodescr = '問題描述';
$lang->milestone->reviewHoursTip = '評審工作量 = 評審時長 * 評審人數';
$lang->milestone->toHoursTip = '返工工作量統計的是研發任務被激活之後,重新消耗的工時';
$lang->milestone->quality = new stdclass();
$lang->milestone->quality->total = '合計';
$lang->milestone->quality->identify = '缺陷識別階段';
$lang->milestone->quality->injection = '缺陷注入階段';
$lang->milestone->quality->scale = '規模';
$lang->milestone->quality->identifyRate = '缺陷識別率';
$lang->milestone->quality->injectionRate = '缺陷注入率';
$lang->milestone->options = '操作';
$lang->milestone->milestoneHelpNotice = <<<EOD
<h2>PV 計劃完成的工作</h2>
計算方式:
<br />1任務所屬階段是當前里程碑累加預計工時
<br />2當前里程碑階段之前的所有階段下的任務累加預計工時
<p>統計範圍:</p>
1為避免重複計算只包含子任務不包括父任務
<br />2不包括已刪除的任務
<br />3不包括已取消的任務
<br />4不包括已刪除執行中的任務
<h2>EV實際完成的工作</h2>
計算方式:
<br />1任務所屬階段是當前里程碑
<br />&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;任務狀態為已完成,累加預計工時
<br />&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;任務狀態為已關閉且關閉原因為已完成,累加預計工時
<br />&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;任務狀態為進行中、已暫停,累加 預計工時×完成進度
<br />2當前里程碑階段之前的所有階段下的任務
<br />&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;任務狀態為已完成,累加預計工時
<br />&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;任務狀態為已關閉且關閉原因為已完成,累加預計工時
<br />&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;任務狀態為進行中、已暫停,累加 預計工時×完成進度
<p>統計範圍:</p>
1為避免重複計算只包含子任務不包括父任務
<br />2不包括已刪除的任務
<br />3不包括已取消的任務
<br />4不包括已刪除執行中的任務
<br />5消耗工時不為0的任務
<br />6完成進度=已消耗工時÷(已消耗工時+剩餘工時)
<h2>AC 實際花費(消耗)的成本</h2>
計算方式:
<br />1當前里程碑中所有消耗的工時
<br />2當前里程碑階段之前的所有階段下消耗的工時
<p>統計範圍:</p>
1消耗的工時包括任務、需求、Bug、用例、版本、測試單、問題、風險、文檔、評審的耗時
<br />2為避免重複計算只包含子任務不包括父任務
<br />3包括已刪除的任務、需求、Bug、用例、版本、測試單、問題、風險、文檔、評審的耗時
<br />4包括已刪除執行中任務、需求、Bug、用例、版本、測試單、文檔的耗時
<br />5包括取消的任務、問題、風險的耗時
<h2>SV(%)進度偏差率</h2>
計算方式SV(%) = -1 * (1 - (EV / PV))%
<h2>CV(%) 成本偏差率</h2>
計算方式CV(%) = -1 * (1 - (EV / AC))%
<h2>SPI 進度性能指標</h2>
計算方式SPI = EV / PV
<h2>CPI成本性能指標</h2>
計算方式CPI = EV / AC
EOD;
$lang->milestone->soFarHelpNotice = <<<EOD
<h2>PV計劃完成的工作</h2>
計算方式:
<br />1任務預計截止日期在今天結束時間之前累加預計工時
<br />2任務預計開始日期小於今天結束時間截止日期大於今天結束時間累加任務的預計工時 ÷ 任務工期天數)× 任務預計開始到本週結束日期的天數
<p>統計範圍:</p>
1為避免重複計算只包含子任務不包括父任務
<br />2不包括刪除的任務
<br />3不包括取消的任務
<br />4不包括已刪除執行中的任務
<br />5今天結束時間是今天的23:59:59
<br />6任務未填寫預計開始日期預計開始日期預設取任務所屬階段的計劃開始日期
<br />7任務未填寫預計截止日期預計截止日期預設取任務所屬階段的計劃完成日期
<br />8計算公式只計算工作日
<h2>EV實際完成的工作</h2>
計算方式:
<br />1任務狀態為已完成累加預計工時
<br />2任務狀態為已關閉且關閉原因為已完成累加預計工時
<br />3任務狀態為進行中、已暫停累加 預計工時×完成進度
<p>統計範圍:</p>
1今天結束時間之前今天結束時間是今天的23:59:59
<br />2為避免重複計算只包含子任務不包括父任務
<br />3不包括已刪除的任務
<br />4不包括已取消的任務
<br />5不包括已刪除執行中的任務
<br />6消耗工時不為0的任務
<br />7完成進度=已消耗工時÷(已消耗工時+剩餘工時)
<h2>AC 實際花費(消耗)的成本</h2>
計算方式:
<br />1累加今天結束時間之前所有消耗的工時
<p>統計範圍:</p>
1消耗的工時包括任務、需求、Bug、用例、版本、測試單、問題、風險、文檔、評審的耗時
<br />2為避免重複計算只包含子任務不包括父任務
<br />3包括已刪除的任務、需求、Bug、用例、版本、測試單、問題、風險、文檔、評審的耗時
<br />4包括已刪除執行中任務、需求、Bug、用例、版本、測試單、文檔的耗時
<br />5包括取消的任務、問題、風險的耗時
<br />6今天結束時間是今天的23:59:59
<h2>SV(%)進度偏差率</h2>
計算方式SV(%) = -1 * (1 - (EV / PV))%
<h2>CV(%) 成本偏差率</h2>
計算方式CV(%) = -1 * (1 - (EV / AC))%
<h2>SPI 進度性能指標</h2>
計算方式SPI = EV / PV
<h2>CPI成本性能指標</h2>
計算方式CPI = EV / AC