$lang->milestone->common = $lang->projectCommon . '里程碑報告';
|
||
$lang->milestone->index = '報告首頁';
|
||
$lang->milestone->title = '里程碑報告';
|
||
$lang->milestone->name = '里程碑名稱';
|
||
$lang->milestone->stage = '里程碑階段';
|
||
$lang->milestone->save = '保存';
|
||
|
||
$lang->milestone->indexAction = '里程碑報告';
|
||
|
||
$lang->milestone->startedWeeks = '開始周數';
|
||
$lang->milestone->finishedWeeks = '結束周數';
|
||
$lang->milestone->offset = '里程碑工期偏差';
|
||
|
||
$lang->milestone->processCommon = $lang->projectCommon . '當前進展狀況';
|
||
$lang->milestone->process = $lang->projectCommon . '進度';
|
||
$lang->milestone->executionCost = $lang->projectCommon . '成本';
|
||
$lang->milestone->toNow = '到目前為止';
|
||
$lang->milestone->targetRange = '目標控制範圍';
|
||
$lang->milestone->ge = '大於等於';
|
||
$lang->milestone->le = '小於等於';
|
||
$lang->milestone->analysis = '分析結果';
|
||
$lang->milestone->PV = '計劃完成的工作(PV)';
|
||
$lang->milestone->EV = '實際完成的工作(EV)';
|
||
$lang->milestone->AC = '實際花費的成本(AC)';
|
||
$lang->milestone->SPI = $lang->projectCommon . '進度績效(SPI)';
|
||
$lang->milestone->CPI = $lang->projectCommon . '成本績效(CPI)';
|
||
$lang->milestone->SV = '進度偏差率(SV%)';
|
||
$lang->milestone->CV = '成本偏差率(CV%)';
|
||
|
||
$lang->milestone->workHours = '工作量(人時)';
|
||
$lang->milestone->allStage = '工程階段';
|
||
$lang->milestone->devHours = '研發工作量';
|
||
$lang->milestone->toHours = '返工工作量';
|
||
$lang->milestone->reviewHours = '評審工作量';
|
||
$lang->milestone->qaHours = '測試工作量';
|
||
$lang->milestone->rowSummary = '工作量小計';
|
||
$lang->milestone->rowPercent = '分佈百分比(%)';
|
||
$lang->milestone->colPercent = '占工作量百分比(%)';
|
||
$lang->milestone->colSummary = '總和';
|
||
$lang->milestone->qatoDev = '測試研發比';
|
||
|
||
$lang->milestone->executionRisk = '5.' . $lang->projectCommon . '風險(優先最高的前五項風險)';
|
||
$lang->milestone->riskCountermove = '風險對策';
|
||
$lang->milestone->riskDescriptio = '風險描述';
|
||
$lang->milestone->riskPossibility = '可能性';
|
||
$lang->milestone->riskSeriousness = '嚴重性';
|
||
$lang->milestone->riskFactor = '風險係數';
|
||
$lang->milestone->riskMeasures = '風險對策';
|
||
$lang->milestone->riskAccumulate = '累積的高風險';
|
||
|
||
$lang->milestone->otherIssue = '其它問題';
|
||
$lang->milestone->issueSolutions = '問題及解決建議';
|
||
$lang->milestone->issueDescription = '問題描述';
|
||
$lang->milestone->issuePropose = '解決建議';
|
||
|
||
$lang->milestone->demandStatus = '4.用戶需求狀況分析';
|
||
$lang->milestone->storyUnit = '單位:Item';
|
||
$lang->milestone->engineeringStage = '工程階段';
|
||
$lang->milestone->rateChange = '需求變化率';
|
||
$lang->milestone->originalStory = '原始需求數量';
|
||
$lang->milestone->modifyNumber = '變更後需求總數';
|
||
$lang->milestone->changeStory = '變更的需求數';
|
||
|
||
$lang->milestone->paogressForecast = $lang->projectCommon . '進展預測';
|
||
$lang->milestone->duration = '工期(天)';
|
||
$lang->milestone->cost = '成本(人時)';
|
||
$lang->milestone->forecastResults = '預測結果分析';
|
||
$lang->milestone->plannedValue = '計劃值';
|
||
$lang->milestone->predictedValue = '預測值';
|
||
$lang->milestone->predictedValueDesc = '計算公式:如果' . $lang->projectCommon . '進度績效(SPI)=0,那麼預測值=0,否則,預測值=計劃值 除以 ' . $lang->projectCommon . '進度績效(SPI)';
|
||
$lang->milestone->periodDeviation = '工期偏差';
|
||
$lang->milestone->costDeviation = '成本偏差';
|
||
$lang->milestone->nextStage = '下一里程碑階段';
|
||
$lang->milestone->overallProject = $lang->projectCommon . '總體';
|
||
$lang->milestone->corrective = '糾偏措施';
|
||
$lang->milestone->timeOverrun = '總工期將超出:%s天。';
|
||
$lang->milestone->costOverrun = '總成本將超出:%s個單位。';
|
||
$lang->milestone->saveOtherProblem = '保存其他問題';
|
||
|
||
$lang->milestone->chart = new stdclass();
|
||
$lang->milestone->chart->title = '到目前為止' . $lang->projectCommon . '進展趨勢圖';
|
||
$lang->milestone->chart->time = '第';
|
||
$lang->milestone->chart->week = '周';
|
||
$lang->milestone->chart->month = '月';
|
||
$lang->milestone->chart->workhour = '研發工作量分析圖';
|
||
|
||
$lang->milestone->otherproblem = '6.其它問題';
|
||
$lang->milestone->problemandsuggest = '問題及解決建議';
|
||
$lang->milestone->suggest = '解決建議';
|
||
$lang->milestone->needhelp = '是否需要高層支持?';
|
||
$lang->milestone->prodescr = '問題描述';
|
||
|
||
$lang->milestone->reviewHoursTip = '評審工作量 = 評審時長 * 評審人數';
|
||
$lang->milestone->toHoursTip = '返工工作量統計的是研發任務被激活之後,重新消耗的工時';
|
||
|
||
$lang->milestone->quality = new stdclass();
|
||
$lang->milestone->quality->total = '合計';
|
||
$lang->milestone->quality->identify = '缺陷識別階段';
|
||
$lang->milestone->quality->injection = '缺陷注入階段';
|
||
$lang->milestone->quality->scale = '規模';
|
||
$lang->milestone->quality->identifyRate = '缺陷識別率';
|
||
$lang->milestone->quality->injectionRate = '缺陷注入率';
|
||
|
||
$lang->milestone->options = '操作';
|
||
|
||
$lang->milestone->milestoneHelpNotice = <<<EOD
|
||
<h2>PV 計劃完成的工作</h2>
|
||
計算方式:
|
||
<br />1)任務所屬階段是當前里程碑,累加預計工時
|
||
<br />2)當前里程碑階段之前的所有階段下的任務,累加預計工時
|
||
<p>統計範圍:</p>
|
||
1)為避免重複計算,只包含子任務,不包括父任務
|
||
<br />2)不包括已刪除的任務
|
||
<br />3)不包括已取消的任務
|
||
<br />4)不包括已刪除執行中的任務
|
||
<h2>EV實際完成的工作</h2>
|
||
計算方式:
|
||
<br />1)任務所屬階段是當前里程碑:
|
||
<br /> 任務狀態為已完成,累加預計工時
|
||
<br /> 任務狀態為已關閉且關閉原因為已完成,累加預計工時
|
||
<br /> 任務狀態為進行中、已暫停,累加 預計工時×完成進度
|
||
<br />2)當前里程碑階段之前的所有階段下的任務:
|
||
<br /> 任務狀態為已完成,累加預計工時
|
||
<br /> 任務狀態為已關閉且關閉原因為已完成,累加預計工時
|
||
<br /> 任務狀態為進行中、已暫停,累加 預計工時×完成進度
|
||
<p>統計範圍:</p>
|
||
1)為避免重複計算,只包含子任務,不包括父任務
|
||
<br />2)不包括已刪除的任務
|
||
<br />3)不包括已取消的任務
|
||
<br />4)不包括已刪除執行中的任務
|
||
<br />5)消耗工時不為0的任務
|
||
<br />6)完成進度=已消耗工時÷(已消耗工時+剩餘工時)
|
||
<h2>AC 實際花費(消耗)的成本</h2>
|
||
計算方式:
|
||
<br />1)當前里程碑中所有消耗的工時
|
||
<br />2)當前里程碑階段之前的所有階段下消耗的工時
|
||
<p>統計範圍:</p>
|
||
1)消耗的工時包括任務、需求、Bug、用例、版本、測試單、問題、風險、文檔、評審的耗時
|
||
<br />2)為避免重複計算,只包含子任務,不包括父任務
|
||
<br />3)包括已刪除的任務、需求、Bug、用例、版本、測試單、問題、風險、文檔、評審的耗時
|
||
<br />4)包括已刪除執行中任務、需求、Bug、用例、版本、測試單、文檔的耗時
|
||
<br />5)包括取消的任務、問題、風險的耗時
|
||
<h2>SV(%)進度偏差率</h2>
|
||
計算方式:SV(%) = -1 * (1 - (EV / PV))%
|
||
<h2>CV(%) 成本偏差率</h2>
|
||
計算方式:CV(%) = -1 * (1 - (EV / AC))%
|
||
<h2>SPI 進度性能指標</h2>
|
||
計算方式:SPI = EV / PV
|
||
<h2>CPI成本性能指標</h2>
|
||
計算方式:CPI = EV / AC
|
||
EOD;
|
||
$lang->milestone->soFarHelpNotice = <<<EOD
|
||
<h2>PV計劃完成的工作</h2>
|
||
計算方式:
|
||
<br />1)任務預計截止日期在今天結束時間之前,累加預計工時
|
||
<br />2)任務預計開始日期小於今天結束時間,截止日期大於今天結束時間,累加(任務的預計工時 ÷ 任務工期天數)× 任務預計開始到本週結束日期的天數
|
||
<p>統計範圍:</p>
|
||
1)為避免重複計算,只包含子任務,不包括父任務
|
||
<br />2)不包括刪除的任務
|
||
<br />3)不包括取消的任務
|
||
<br />4)不包括已刪除執行中的任務
|
||
<br />5)今天結束時間是今天的23:59:59
|
||
<br />6)任務未填寫預計開始日期,預計開始日期預設取任務所屬階段的計劃開始日期
|
||
<br />7)任務未填寫預計截止日期,預計截止日期預設取任務所屬階段的計劃完成日期
|
||
<br />8)計算公式只計算工作日
|
||
<h2>EV實際完成的工作</h2>
|
||
計算方式:
|
||
<br />1)任務狀態為已完成,累加預計工時
|
||
<br />2)任務狀態為已關閉且關閉原因為已完成,累加預計工時
|
||
<br />3)任務狀態為進行中、已暫停,累加 預計工時×完成進度
|
||
<p>統計範圍:</p>
|
||
1)今天結束時間之前,今天結束時間是今天的23:59:59
|
||
<br />2)為避免重複計算,只包含子任務,不包括父任務
|
||
<br />3)不包括已刪除的任務
|
||
<br />4)不包括已取消的任務
|
||
<br />5)不包括已刪除執行中的任務
|
||
<br />6)消耗工時不為0的任務
|
||
<br />7)完成進度=已消耗工時÷(已消耗工時+剩餘工時)
|
||
<h2>AC 實際花費(消耗)的成本</h2>
|
||
計算方式:
|
||
<br />1)累加今天結束時間之前所有消耗的工時
|
||
<p>統計範圍:</p>
|
||
1)消耗的工時包括任務、需求、Bug、用例、版本、測試單、問題、風險、文檔、評審的耗時
|
||
<br />2)為避免重複計算,只包含子任務,不包括父任務
|
||
<br />3)包括已刪除的任務、需求、Bug、用例、版本、測試單、問題、風險、文檔、評審的耗時
|
||
<br />4)包括已刪除執行中任務、需求、Bug、用例、版本、測試單、文檔的耗時
|
||
<br />5)包括取消的任務、問題、風險的耗時
|
||
<br />6)今天結束時間是今天的23:59:59
|
||
<h2>SV(%)進度偏差率</h2>
|
||
計算方式:SV(%) = -1 * (1 - (EV / PV))%
|
||
<h2>CV(%) 成本偏差率</h2>
|
||
計算方式:CV(%) = -1 * (1 - (EV / AC))%
|
||
<h2>SPI 進度性能指標</h2>
|
||
計算方式:SPI = EV / PV
|
||
<h2>CPI成本性能指標</h2>
|
||
計算方式:CPI = EV / AC
|
||